WDM Ltd Road Assessment VehicleOriginally uploaded to Coppermine on Jun 15, 2007 by J--M--B
WDM Ltd Road Assessment VehicleOriginally uploaded to Coppermine on Jun 15, 2007 by J--M--B
WDM Ltd Road Assessment VehicleOriginally uploaded to Coppermine on Jun 15, 2007 by J--M--B
1950 Kenyon advert
Kenyon's made paraffin road warning lamps as you can see here.
Originally uploaded to Coppermine on Jan 27, 2007 by Mikeya
I think they noticed me...
.... and moved the van. :(
Originally uploaded to Coppermine on Jun 01, 2006 by BigToe
Keep right arrow in front of parked van.
... but it seems they have other ideas on where to stick the sign.
Originally uploaded to Coppermine on Jun 01, 2006 by BigToe
Roadworks
That goes into the road a bit... shouldn't there be a keep right sign?
Originally uploaded to Coppermine on Jun 01, 2006 by BigToe
D A3 Roadworks
Roadworks on the A3 in Germany just south of Cologne. Yellow markings are used to indicate 'temporary' (these are red in other countries, such as Austria).
Originally uploaded to Coppermine on Jul 27, 2006 by IJP1
The Mountain Road is Closed (C) Andy Stephenson The scene on the TT course, looking back from the Creg ny Baa.
Cones hotline
Typical, loads of cones and no-one working. Looking west towards Lulworth and Portland, along the South West Coast Path.
Originally uploaded to Coppermine on Jun 11, 2008 by SteveA30
Driving on the railway line (C) John Allan A section of the railway on the south shore of Loch Carron put to use as a temporary way for road vehicles during the long closure of the A890. The road was blocked by a landslide in December 2011 resulting in a diversion of some 140 miles.
A relief ferry <a href='http://www.geograph.org.uk/photo/2812302'>NG8635 : Ferry, Strome Ferry</a> was used to relieve the situation for a while until the railway was prepared to take traffic for short periods during the day.
Some of the work to try to stabilise the cliffs can be seen on the left of the picture.
The road is expected to reopen towards the end of April 2012.
Slip forming machine constructing a concrete step barrier on the M74 Completion project, near junction 2A.
Slip forming machine constructing a concrete step barrier on the M74 Completion project, near junction 2A.
Slip forming machine constructing a concrete step barrier on the M74 Completion project, near junction 2A.
M74 Completion project under construction, looking East at junction 2 at Rutherglen.
Following the rapid replacement of the carriageway following the flash-flood in Coverack in July 2017, there remained remedial works requiring these temporary traffic lights.
Quite a bit of road work starting on the M6 between Stafford and Stoke now, especially on the central reservation. No doubt its probably part of the planned up and coming Smart Motorway scheme. Must of only started work here very recently.
Quite a bit of road work starting on the M6 between Stafford and Stoke now, especially on the central reservation. No doubt its probably part of the planned up and coming Smart Motorway scheme. Must of only started work here very recently.
Wolverhampton tram extension works. The new extension is almost complete and ready but won't open probably until the train station is redeveloped. All Ive noticed so far is that they've started installing new lighting columns.
Wolverhampton tram extension works. The new extension is almost complete and ready but won't open probably until the train station is redeveloped. I noticed that they've started installing new lighting and columns for now. The lanterns here being installed are Philips Lumas, replacing mainly 1960s columns with Holophane QSM lanterns.
Along Railway Drive. Philips MA30 lantern outside Wolverhampton train station. Both this lantern and the column won't be lasting for much longer, as the station is being redeveloped.
Meriden Street, Digbeth, Birmingham. Heading away from Curzon Street. Eventually this whole area is to be redeveloped from what Ive seen. I think theres plans for a metro/tram line down this road too.
The tram extension works in Blackpool, where progress has stopped for now. This Wilko supermarket building is still yet to be demolished to make way for the rest of the new planned tram line.
Wolverhampton tram/metro extension under construction back in July 2018.
Wolverhampton tram/metro extension under construction back in October 2018.
Redevelopment of junction 10 of the M6 well underway. This shot shows where they're digging up and probably widening the sliproads.
Redevelopment of junction 10 of the M6 well underway. This shot shows where they're starting to build the pillars for one of the new bridges.
Along Castle Hill in Dudley, where they're building a new tram/metro line to Merry Hill.
Along Broad Street in Birmingham, where they're building a new tram/metro line. The road is closed off, so there is temporary signage such as 'road closed' and 'diversion'.
School Street in Wolverhampton, where there is road works and even a building being demolished.
Now, in 1928, here we had a stone cutting machine that could do that in a fraction of the time! Mind you, there's no shortage of hard labour about either!!!
You can also view this image, and many thousands of others, on the NLI’s catalogue at <a href='http://catalogue.nli.ie' rel='noreferrer nofollow'>catalogue.nli.ie</a>